Another specialised product that Rocla used in Phase 2 of the project was the HDPE (High Density Polyethylene) liner, manufactured by Engineered Linings. The HDPE liners can withstand aggressive water conditions inside the pipes, which assists in prolonging the lifespan of the sewer system. Rocla used a 3mm thick lining with 10 mm knobs, which can sustain approximately 40 kg of reverse pull forces.
Rocla custom-made a 45 degree pipe using a top cast mould, where each bend is divided into two components, each with a 22.5 degree bend, instead of the normal lobster back bend with corners and edges.
According to Hendrik Stander, Rocla's Sales Executive at the Blackheath plant, manufacturing the bend in two parts means that the handling of the bend is easier and quicker. Each bend weighs 6.3 tons per 22.5 degree bend.
"One of the trickier parts of this particular project", adds Stander "was laying the bended pipes in the correct position of up to 6 metres deep. Access holes were precast into the bends to ensure easy access during inspection. Manhole rings will be placed on top of these access holes to facilitate easy inspection."
To further facilitate the free flow system, Rocla Blackheath designed a 90 degree bend which is divided into three 30 degree bends. "The thrust block on the bend played a dual role in supporting the seam and the bend in the ground", says Stander
Kempen van Wyk, Director of Exeo Khokela Construction, the project's main contractor says, “Rocla has delivered timeously on all deadlines so far. Their constant communication with us regarding manufacturing and our visits to their Blackheath plant ensured that the project has run smoothly from the start. Our close working relationship has played an important role in delivering a customised solution for Drakenstein municipality."
Phase 1 of the project is 60% complete and Phase 2 recently commenced with completion scheduled for December 2010. |